SC – Supply Contract

Updated over a week ago

Suitable for any supply-based contract between a Client and a Supplier. It is intended for the procurement of goods and associated services across a variety of sectors, including infrastructure, building, energy, manufacturing, and transport.

The SC contract type is a core option within the NEC3 family. It is commonly used for the supply of complex equipment, components, plant materials, or systems for projects in infrastructure, highways, and industrial settings.

The key parties on the NEC4 SC type of contract are:

Supply Manager

This is the Client’s role under the contract. The Supply Manager acts as the key contact within the Client organisation, responsible for administering the contract and ensuring its performance.

Supplier

This outlines the supplier’s role in the contract. The Supplier is the organisation or entity providing the goods and related services to the Client and is the main point of contact for delivery.

In the Asite NEC3 Contract Manager, most of the roles used in your contract process may already be defined in the project to which you are given access. See examples below:

  • NEC-SC-Purchaser View Only

  • NEC-SC-Supplier

  • NEC-SC-Supply Manager

  • NEC-SC-Supplier View Only

Roles and Responsibilities

Roles

Responsibilities / Key Activities

Supplier

- Raise early warnings related to delay, cost, or performance issues
- Raise Compensation Events
- Submit quotations as requested
- Submit assessments for the remaining supply amounts
- Notify the Supply Manager of proposed scope changes
- Submit revised delivery schedules if required
- Communicate internally with the contract delivery team
- Raise late notices where applicable
- Request extensions to the delivery or completion period

Supply Manager

- Raise a contract
- Raise early warnings related to delay, cost, or performance
- Review and accept the Supplier’s submissions
- Decide on key delivery milestones or completion dates
- Instruct the Supplier to submit/revise quotations
- Accept or reject submitted quotations
- Notify the Supplier of Compensation Events
- Issue assessments against Compensation Events
- Review and assess submitted Compensation Events
- Approve extensions to the supply period
- Issue completion or delivery certificates
- Certify final payments and manage contract closure or termination actions

NEC SC Contract Forms

A. Contract Information

  • 01a Contract Data & Report

  • 01b Distribution Setup

B. Early Warning

  • 02 EWN by Supplier

  • 03 EWN by Supply Manager

C. Compensation Event Process

  • 04 Supply Manager Instruction

  • 05 NCE by Supplier

  • 06 NCE by Supply Manager

  • 07 Instruction to Submit Quotation

  • 08 Incidents Assessment

  • 09 Quotation by Supplier

  • 10 Supply Manager Assessment

  • 11 Extend Period for Reply

  • 12 Notice of Late Supply Manager's Reply

D. Communications

  • 13 Supplier's Communication

  • 14 Supply Manager Communication

E. Certificates

  • 15 Completion Certificate

  • 16 Sectional Completion Certificate

  • 17 Certificate of Payment Application

  • 18 Payment Certificate

  • 19 Defect Notification by Supply Manager

F. Programme Mgmt

  • 20 Programme Submission