View the Working Calendar on a Project

This article helps you understand how to view working calendar as defined on your projects.

Updated this week

You can view the working calendar in your accessible projects. It lists working days and a list of holidays for each year, as defined in the project.

Click here for detailed help on how to manage a working calendar. Below are the steps to view an existing working calendar:

  1. In the thumbnail view, hover your mouse over the project thumbnail and click the calendar icon.

    Alternately, right-click the project record in the list view and select 'Working Calendar'.

  2. A layered screen appears. It displays the working days and a list of holidays defined in the project.