Skip to main content
Completion Certificate
Updated over a month ago

Click on a relevant link below to continue:

A. Create New '17 Completion Certificate'

It can be created by users in Project Manager role by going to 'Project Forms' or 'Contracts' area as applicable.

Expand the 'E. Certificates' group and select '17 Completion Certificate' type.

Click on '+ Create Form' to create a new '17 Completion Certificate'.

B. Enter Details for '17 Completion Certificate'

This form is used by Project Manager to certify Contractor for the contract completion. Below is a description of the available fields:

B1. Contract Search

To use the search options available - contract code and contract description - to search the contract for which Completion Certificate is to be raised. This would be specifically helpful in cases when you have a long list of contracts and you need to filter out the required contract from the list.

B2. Contract

To select the contract for which Completion Certificate is to be raised. You cannot proceed further with this form without selecting a contract. Based on the contract selected, some of the information may get auto-filled in the form.

B3. To Contractor

To select the Contractor for sending them Completion Certificate.

B4. Section

To select the section applicable in the contract for this Completion Certificate. Click here for detailed help on contract sections.

B5. Subject

Enter a subject line for this Completion Certificate.

B6. Under clause 30.2 the date of completion of the whole of the works is

Displays the date of completion of all contract works with an option to select a new completion date from the calendar if required.

B7. Date of this Completion certificate

Displays the date when this completion certificate is issued.

Entering Distribution List

B11 Add New Recipient

To add new recipients in form distribution list, you need to click on 'Add New Recipient' option available at bottom left of this form section. It will open a layered screen with options to enter details regarding distribution for each recipient added to the form.

B11.1 Recipient User

To select users for form distribution.

B11.2 Form Actions

To select form tasks that needs to be distributed to the selected recipient user.

B11.3 Action Due

To select due date for selected form actions based on the selected recipient user.

Note - While distributing 'For Information' form action, it is not mandatory to select a due date; however, it would be required if distributing other types of form task.

This distribution list may get auto populated based on pre-defined distribution groups if already created for the section selected for this form.

Note: You may add recipients to the distribution of this form by using the 'Add New Recipient' option. Recipients that you add here will be remembered by the form even when saving a draft. Alternately, you may also use the Ad-Hoc distribution module above to add other recipients. However, if you use the Ad-Hoc distribution module when assigning a 'Review Draft' action, that action will not be remembered by the form after the recipient reviews it.

Entering Reference Document Details

B12 Click here to add Reference Document details

To add new reference document details, you need to click on 'Click here to add Reference Document details' option available at bottom left of this form section. It will add a new row wherein you can fill details regarding description of reference document and include hyperlink for the same.

To attach external files as reference documents, click here for detailed help on how to attach files while creating a form.

To associate existing files on the projects accessible to you on Asite, click here for detailed help on how to associate files while creating a form.

B12.1 Description

To enter a description of the reference document that you are adding.

B12.2 Hyperlink

To enter a hyperlink for the corresponding reference document description.

C. Submit Details for '17 Completion Certificate' / Save Details as Draft

Once you have entered the required details, click 'Send' button to save / submit the details. This will send a 'For Information' task to the Contractor. Also, the form will be distributed separately as per the distribution list entered while creating the form if any.

In case you plan to edit and submit later, use the 'Save Draft' button to save the details as a draft. In such a scenario, you have an option to get the draft message reviewed by some other user by assigning them 'Review Draft' task. Users who are added as 'Draft Only' members in the contract management team will only be able to save the form details as a draft and cannot 'Send' the form.

Click 'Cancel' if you want to entirely cancel the form under creation. Clicking on 'Cancel' will prompt the user to confirm once again as any unsaved data in the form under creation will be lost forever once it is cancelled.

D. Edit Draft of '17 Completion Certificate'

Click here for detailed help on how to edit an existing form draft.

E. View Existing '17 Completion Certificate'

To open an existing '17 Completion Certificate' form for viewing, click on the form title from relevant listing area. The form will open in view mode as shown below.

Click here for detailed help on Form Viewer Options.

Click on the contract number to view related contract details. Similarly, click on any of the form id's with hyperlink to open related form as applicable.



Did this answer your question?